SPP-GEN-2023-221
250 MW generation in Osage, KS · In queue since October 2023 · Proposed COD December 2029
250 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
SPP-GEN-2023-221 is a proposed solar generation project with a total capacity of 250 MW. The project is located in Osage County, Kansas, and falls within the Southwest Power Pool (SPP) service area, interconnecting to the Emporia Energy Center - Swissvale 345 kV Line. The queue entry date is October 2, 2023, with a proposed commercial operation date of December 1, 2029. The interconnecting utility is Evergy.
The project's interconnection status is currently in the System Impact Study phase within the SPP queue. The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
KS
County
Osage
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
Evergy
Entity
SPP
Service Type
—
Point of Interconnection
Emporia Energy Center - Swissvale 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Center St
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2023-221