SPP-GEN-2023-223
239 MW generation in Gage, NE · In queue since October 2023 · Proposed COD June 2027
239 MW
Capacity
1
Components
Gas
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
3y 8m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-06-01
SPP-GEN-2023-223 is a proposed generation project located in Gage County, Nebraska, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 239 MW, is being developed by NPPD and utilizes gas-fired technology. It entered the SPP interconnection queue on October 2, 2023, and has a proposed commercial operation date of June 1, 2027.
Currently, the project's interconnection status is in the System Impact Study phase. The point of interconnection (POI) is the New Beatrice Power Station 345 kV.
Generated from interconnection queue and public data sources
State
NE
County
Gage
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
—
Point of Interconnection
New Beatrice Power Station 345 kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2023-223