SPP-GEN-2023-229
230 MW generation in Caddo, OK · In queue since October 2023 · Proposed COD October 2028
230 MW
Capacity
1
Components
Wind
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
5 years
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-10-31
SPP-GEN-2023-229 is a proposed 230 MW wind generation project located in Caddo County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 2, 2023, and a proposed commercial operation date of October 31, 2028. The interconnecting utility is AEP.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Southwestern Power Station 138 kV Substation (SWS4).
Generated from interconnection queue and public data sources
State
OK
County
Caddo
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Southwestern Power Station 138 kV Substation (SWS4)
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Substation