SPP-GEN-2023-241
93 MW generation in Franklin, TX · In queue since October 2023 · Proposed COD January 2028
93 MW
Capacity
1
Components
Solar
2y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 3m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-01-05
SPP-GEN-2023-241 is a proposed 93 MW solar generation project located in Franklin County, Texas. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 2, 2023. The proposed commercial operation date is January 5, 2028. The interconnection request is currently in the System Impact Study phase. The interconnecting utility is AEP, and the point of interconnection (POI) is the Winnsboro 138 kV Substation.
The development project consists of 93 MW of solar photovoltaic generation. It is currently listed as active in the SPP queue.
Generated from interconnection queue and public data sources
State
TX
County
Franklin
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Winnsboro 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Winnsboro Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.