SPP-GEN-2023-SR7
135 MW storage in Wayne, NE · In queue since December 2022 · Proposed COD December 2024
135 MW
Capacity
1
Components
Battery
3y 5m
In Queue
Facility Study
IA Status
COD target: 2024
Total Duration
2 years
Schedule
16 months past proposed COD
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2024-12-31
SPP-GEN-2023-SR7 is a proposed 135 MW battery storage project located in Wayne County, Nebraska. The project, which consists entirely of battery storage, is in the Southwest Power Pool (SPP) interconnection queue as of December 16, 2022. The proposed commercial operation date is December 31, 2024. The interconnecting utility is Nebraska Public Power District (NPPD).
The project's interconnection status is currently in the Facility Study phase. The point of interconnection is the Hoskins 345 kV Substation. The project has appeared in recent news coverage regarding SPP's interconnection queue.
Generated from interconnection queue and public data sources
State
NE
County
Wayne
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
—
Point of Interconnection
Hoskins 345 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Hoskins Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.