SPP-GEN-2024-021
540 MW generation in Lancaster, NE · In queue since October 2024 · Proposed COD December 2030
540 MW
Capacity
1
Components
Gas
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
SPP-GEN-2024-021 is a proposed 540 MW gas-fired generation project located in Lancaster County, Nebraska. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 30, 2024. The proposed commercial operation date is December 31, 2030. Nebraska Public Power District (NPPD) is the utility.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Olive Creek 345 kV Substation.
Generated from interconnection queue and public data sources
State
NE
County
Lancaster
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
—
Point of Interconnection
Olive Creek 345 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.