SPP-GEN-2024-023
270 MW generation in Gage, NE · In queue since October 2024 · Proposed COD December 2030
270 MW
Capacity
1
Components
Gas
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2030
Total Duration
6y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2030-12-31
SPP-GEN-2024-023 is a proposed 270 MW natural gas generation project located in Gage County, Nebraska. The project is listed in the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-GEN-2024-023, with an entry date of October 30, 2024. The proposed commercial operation date is December 31, 2030. Nebraska Public Power District (NPPD) is the interconnecting utility.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the New Beatrice Power Station 345 kV substation. The project consists of 270 MW of natural gas-fired generation capacity.
Generated from interconnection queue and public data sources
State
NE
County
Gage
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
—
Point of Interconnection
New Beatrice Power Station 345 kV
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-023