SPP-GEN-2024-029
150 MW storage in Logan, OK · In queue since October 2024 · Proposed COD December 2028
150 MW
Capacity
1
Components
Battery
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
SPP-GEN-2024-029 is a proposed 150 MW battery storage project located in Logan County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 30, 2024. The proposed commercial operation date is December 31, 2028.
The interconnection request is currently in the System Impact Study phase. The point of interconnection is the Crescent 138 kV Substation, and Oklahoma Gas & Electric (OGE) is the utility.
Generated from interconnection queue and public data sources
State
OK
County
Logan
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
—
Point of Interconnection
Crescent 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Crescent Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-029