SPP-GEN-2024-032
250 MW generation in Stevens, KS · In queue since October 2024 · Proposed COD December 2028
250 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
SPP-GEN-2024-032 is a proposed solar generation project located in Stevens County, Kansas, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 250 MW, consists entirely of solar photovoltaic generation. The project's interconnection request was entered into the SPP queue on October 30, 2024, with a proposed commercial operation date of December 31, 2028. The interconnection customer is SUNC. The project's interconnection status is currently in the System Impact Study phase.
The point of interconnection (POI) for the project is the Hugoton 115 kV Substation. The project is listed as "active" in the SPP interconnection queue.
Generated from interconnection queue and public data sources
State
KS
County
Stevens
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
—
Point of Interconnection
Hugoton 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-032