Project SPP-GEN-2024-034 — Project Summary

Queue ID
SPP-GEN-2024-034
Capacity
175 MW
Technology
Battery
Status
active
Location
Sargent, ND
Region
SPP
Developer
IA Status
System Impact Study

SPP-GEN-2024-034

SPP-GEN-2024-034BetaActiveBatterySPPLBNL + Live

175 MW storage in Sargent, ND · In queue since October 2024 · Proposed COD July 2029

175 MW

Capacity

1

Components

Battery

1y 7m

In Queue

System Impact Study

IA Status

COD target: 2029

Interconnection

Total Duration

4y 9m

Impact Study25%
Queue EntryOct 30, 2024

Interconnection request submitted to ISO/RTO

DISIS StudyCurrent

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2029-07-01

About

SPP-GEN-2024-034 is a proposed 175 MW battery storage project in Sargent County, North Dakota. The project is located within the Southwest Power Pool (SPP) region and is being developed as a standalone storage facility. The proposed commercial operation date is July 1, 2029, with a queue entry date of October 30, 2024. The point of interconnection is the Forman 115 kV Substation, and the interconnecting utility is Western Area Power Administration (WAPA).

The project's interconnection status is currently in the System Impact Study phase within the SPP queue. The developer is unknown. Recent news coverage of the project could not be confirmed from available data.

Generated from interconnection queue and public data sources

Project Details

State

ND

County

Sargent

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

WAPA

Entity

SPP

Service Type

Point of Interconnection

Forman 115 kV Substation

Data Source

LBNL + Live

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
HIGH
POI Substation
Forman Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.