SPP-GEN-2024-061
200 MW storage in Cowley, KS · In queue since October 2024 · Proposed COD December 2028
200 MW
Capacity
1
Components
Battery
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
SPP-GEN-2024-061 is a proposed 200 MW battery storage project located in Cowley County, Kansas. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 30, 2024, and a proposed commercial operation date of December 31, 2028. The project's interconnection status is currently in the System Impact Study phase.
The project, which interconnects to the Creswell 138 kV Substation, is being proposed within the Western Rivers Energy (WERE) service territory. The project consists of 200 MW of battery storage capacity. The project is listed as active in the SPP queue.
Generated from interconnection queue and public data sources
State
KS
County
Cowley
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
—
Point of Interconnection
Creswell 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Creswell Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-061