SPP-GEN-2024-062
230 MW storage in Kingfisher, OK · In queue since October 2024 · Proposed COD December 2028
230 MW
Capacity
1
Components
Battery
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
SPP-GEN-2024-062 is a proposed 230 MW battery storage project located in Kingfisher County, Oklahoma. The project, which consists of 230 MW of battery capacity, is being developed within the Southwest Power Pool (SPP) interconnection queue under queue ID SPP-GEN-2024-062. The project's point of interconnection is the Dover SW 138 kV Substation, and Western Farmers Electric Cooperative (WFEC) is listed as the utility.
The project entered the SPP queue on October 30, 2024, and has a proposed commercial operation date of December 31, 2028. Its interconnection status is currently in the System Impact Study phase. The project is listed as active within the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Kingfisher
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WFEC
Entity
SPP
Service Type
—
Point of Interconnection
Dover SW 138 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-062