SPP-GEN-2024-065
150 MW storage in Dodge, NE · In queue since October 2024 · Proposed COD December 2029
150 MW
Capacity
1
Components
Battery
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
SPP-GEN-2024-065 is a proposed 150 MW battery storage project located in Dodge County, Nebraska. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on October 30, 2024. The proposed commercial operation date is December 31, 2029. The project's interconnection status is currently in the System Impact Study phase. The interconnecting utility is Nebraska Public Power District (NPPD).
The project consists of 150 MW of battery storage. It is interconnected to the grid at the FREMONT7 115 kV Substation.
Generated from interconnection queue and public data sources
State
NE
County
Dodge
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NPPD
Entity
SPP
Service Type
—
Point of Interconnection
FREMONT7 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-065