SPP-GEN-2024-067
380 MW generation in Cloud, KS · In queue since October 2024 · Proposed COD July 2029
380 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
4y 9m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-07-01
SPP-GEN-2024-067 is a proposed solar generation project located in Cloud County, Kansas, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 380 MW, is being developed in the SUNC utility territory. It entered the SPP interconnection queue on October 30, 2024, and has a proposed commercial operation date of July 1, 2029. The project's interconnection status is currently in the System Impact Study phase.
The proposed project consists of 380 MW of solar photovoltaic generation. The point of interconnection (POI) is the Meridian Way 230 kV Substation. The project is listed as "active" in the SPP interconnection queue.
Generated from interconnection queue and public data sources
State
KS
County
Cloud
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
—
Point of Interconnection
Meridian Way 230 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EDE_MWW
- POI Substation
- Meridian Way 1 Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.