SPP-GEN-2024-068
300 MW generation in Morris, TX · In queue since October 2024 · Proposed COD December 2028
300 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-29
SPP-GEN-2024-068 is a proposed solar generation project located in Morris County, Texas, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 300 MW, consists entirely of solar photovoltaic generation. The interconnection request was entered into the SPP queue on October 30, 2024, with a proposed commercial operation date of December 29, 2028. The interconnecting utility is AEP, and the project's point of interconnection (POI) is the Lydia - Welsh 345 kV Line. The project's interconnection status is currently in the System Impact Study phase.
The development project is listed in the SPP interconnection queue under queue ID SPP-GEN-2024-068.
Generated from interconnection queue and public data sources
State
TX
County
Morris
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Lydia - Welsh 345 kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-068