SPP-GEN-2024-069
228 MW hybrid in Crawford, KS · In queue since October 2024 · Proposed COD December 2028
228 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-12-31
SPP-GEN-2024-069 is a proposed 228 MW hybrid solar and battery project located in Crawford County, Kansas. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on October 30, 2024. The proposed commercial operation date is December 31, 2028. The interconnecting utility is Evergy.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Franklin 69 kV Substation. The project has appeared in recent news coverage.
Generated from interconnection queue and public data sources
State
KS
County
Crawford
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
Evergy
Entity
SPP
Service Type
—
Point of Interconnection
Franklin 69 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Franklin Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-069