SPP-GEN-2024-071
28 MW generation in Cass, TX · In queue since October 2024 · Proposed COD July 2027
28 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2027
Total Duration
2y 9m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2027-07-01
SPP-GEN-2024-071 is a proposed solar generation project located in Cass County, Texas, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 28 MW, consists entirely of solar photovoltaic technology. The interconnection request was entered into the SPP queue on October 30, 2024, with a proposed commercial operation date of July 1, 2027. The interconnecting utility is AEP.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the West Atlanta - Atlanta 69 kV Line. There has been recent news coverage of the project.
Generated from interconnection queue and public data sources
State
TX
County
Cass
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
West Atlanta - Atlanta 69 kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-071