SPP-GEN-2024-077
300 MW generation in Hutchinson, TX · In queue since October 2024 · Proposed COD December 2029
300 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
Proposed project SPP-GEN-2024-077 is a 300 MW solar generation project located in Hutchinson County, Texas. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of October 30, 2024. The proposed commercial operation date is December 1, 2029. The interconnection status is currently in the System Impact Study phase.
The project, which will interconnect at the Pringle 230 kV Substation, is being developed within the service territory of Southwestern Public Service (SPS). The project consists of 300 MW of solar photovoltaic generation capacity.
Generated from interconnection queue and public data sources
State
TX
County
Hutchinson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Pringle 230 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SPS.ORPLPRN1_2
- POI Substation
- Pringle Interchange
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-077