SPP-GEN-2024-079
250 MW generation in Curry, NM · In queue since October 2024 · Proposed COD December 2029
250 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
SPP-GEN-2024-079 is a proposed solar generation project located in Curry County, New Mexico, within the Southwest Power Pool (SPP) region. The project, with a total capacity of 250 MW, consists entirely of solar photovoltaic generation. Its point of interconnection (POI) is the San Juan 230 kV Substation.
The project entered the SPP interconnection queue on October 30, 2024, and has a proposed commercial operation date of December 1, 2029. Its interconnection status is currently in the System Impact Study phase. The interconnecting utility is Southwestern Public Service (SPS).
Generated from interconnection queue and public data sources
State
NM
County
Curry
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
San Juan 230 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SPS.SJUANWIND1
- POI Substation
- San Juan Tap
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.