SPP-GEN-2024-080
250 MW generation in Curry, NM · In queue since October 2024 · Proposed COD December 2029
250 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-01
SPP-GEN-2024-080 is a proposed 250 MW solar generation project located in Curry County, New Mexico. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on October 30, 2024. The proposed commercial operation date is December 1, 2029. The project's interconnection status is currently in the System Impact Study phase.
The project, which will interconnect to Southwestern Public Service (SPS) at the San Juan 230 kV Substation, consists of 250 MW of solar photovoltaic generation. The project is currently listed as active in the SPP queue. Recent news coverage suggests increasing interest in renewable energy projects in the region.
Generated from interconnection queue and public data sources
State
NM
County
Curry
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
San Juan 230 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SPS.SJUANWIND1
- POI Substation
- San Juan Tap
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-080