SPP-GEN-2024-084
167 MW storage in Lawrence, MO · In queue since October 2024 · Proposed COD November 2028
167 MW
Capacity
1
Components
Battery
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2028
Total Duration
4y 1m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2028-11-25
SPP-GEN-2024-084 is a proposed 167 MW battery storage project located in Lawrence County, Missouri. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on October 30, 2024. The proposed commercial operation date is November 25, 2028. The interconnecting utility is AEP.
The project's interconnection status is currently in the System Impact Study phase. The point of interconnection (POI) is the Reeds Spring - Aurora 161 kV Line.
Generated from interconnection queue and public data sources
State
MO
County
Lawrence
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
—
Point of Interconnection
Reeds Spring - Aurora 161 kV Line
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Aurora St
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-084