SPP-GEN-2024-085
160 MW generation in Rush, KS · In queue since October 2024 · Proposed COD September 2029
160 MW
Capacity
1
Components
Solar
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
4y 11m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-09-01
SPP-GEN-2024-085 is a proposed 160 MW solar generation project located in Rush County, Kansas. The project is in the Southwest Power Pool (SPP) interconnection queue as of October 30, 2024, with a proposed commercial operation date of September 1, 2029. The interconnection customer is SUNC. The point of interconnection is the Otis 115 kV Substation. The project's interconnection status is currently in the System Impact Study phase.
The development project consists of 160 MW of solar photovoltaic generation. It is currently listed as an active project within the SPP queue.
Generated from interconnection queue and public data sources
State
KS
County
Rush
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
—
Point of Interconnection
Otis 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Otis Substation