SPP-GEN-2024-092
199.5 MW storage in Roosevelt, NM · In queue since October 2024 · Proposed COD December 2029
199.5 MW
Capacity
1
Components
Battery
1y 7m
In Queue
System Impact Study
IA Status
COD target: 2029
Total Duration
5y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Proposed COD: 2029-12-31
SPP-GEN-2024-092 is a proposed energy storage project located in Roosevelt County, New Mexico, within the Southwest Power Pool (SPP) region. The project, consisting of 199.5 MW of battery capacity, is listed in the SPP interconnection queue as of October 30, 2024. The proposed commercial operation date is December 31, 2029.
The project's interconnection status is currently in the System Impact Study phase. The interconnecting utility is Southwestern Public Service (SPS), and the point of interconnection (POI) is the Portales 115 kV Substation.
Generated from interconnection queue and public data sources
State
NM
County
Roosevelt
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
—
Point of Interconnection
Portales 115 kV Substation
Data Source
LBNL + Live
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Portage
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-092