SPP-GEN-2024-117
150 MW generation in Washington, OK · In queue since March 2025
150 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-117 is a proposed 150 MW solar and battery hybrid project located in Washington County, Oklahoma. The project, which is in the Southwest Power Pool (SPP) interconnection queue, entered the queue on March 1, 2025. The proposed point of interconnection is the Coffeyville Tap - North Bartlesville 138kV Line.
The project consists of both solar and battery storage components, though the individual capacity of each is not specified. The queue status is currently listed as active, and the service type is Energy Resource/Network Resource (ER/NR). The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
OK
County
Washington
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Coffeyville Tap - North Bartlesville 138kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.