SPP-GEN-2024-123
120 MW generation in Shelby, TX · In queue since March 2025
120 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-123 is a proposed 120 MW solar generation project located in Shelby County, Texas. The project is interconnected to the Southwest Power Pool (SPP) via the Center - Tenaha 138 kV Line, with American Electric Power (AEP) as the utility. The project's service type is Energy Resource/Network Resource (ER/NR).
The project entered the SPP interconnection queue on March 1, 2025. As of the latest data, the project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
State
TX
County
Shelby
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Center - Tenaha 138 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Center St
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.