SPP-GEN-2024-124
420 MW generation in Lea, NM · In queue since March 2025
420 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-124 is a proposed 420 MW solar and battery hybrid project located in Lea County, New Mexico. The project, which is listed as active in the Southwest Power Pool (SPP) interconnection queue, entered the queue on March 1, 2025. The proposed point of interconnection is the Crossroads-Hobbs-Roadrunner 345 kV Line.
The project is seeking ER/NR service type from the Northeast New Mexico Electric Transmission System (NEETSW). The technology detail is listed as Hybrid / Solar/Storage.
Generated from interconnection queue and public data sources
State
NM
County
Lea
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NEETSW
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Crossroads-Hobbs-Roadrunner 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-124