SPP-GEN-2024-136
400 MW generation in Scott, KS · In queue since March 2025
400 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-136 is a proposed 400 MW solar photovoltaic generation project located in Scott County, Kansas. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The point of interconnection is the Setab 345 kV Substation.
The project's service type is Energy Resource/Network Resource (ER/NR). The interconnecting utility is Sunflower Electric Power Corporation (SUNC). The project is currently listed as active in the SPP queue.
Generated from interconnection queue and public data sources
State
KS
County
Scott
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Setab 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Setab Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.