SPP-GEN-2024-158
190 MW generation in Jackson, OK · In queue since March 2025
190 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-158 is a proposed 190 MW solar generation project located in Jackson County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The proposed point of interconnection (POI) is the Altus Jct - Snyder 138 kV Line. The project's service type is Energy Resource/Network Resource (ER/NR).
The project is listed as "active" in the SPP queue. American Electric Power (AEP) is the utility associated with the interconnection request.
Generated from interconnection queue and public data sources
State
OK
County
Jackson
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Altus Jct - Snyder 138 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.