SPP-GEN-2024-175
200 MW storage in Greene, MO · In queue since March 2025
200 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-175 is a proposed 200 MW battery storage project located in Greene County, Missouri. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the Summit 161 kV Substation.
The project's service type is listed as ER/NR, and it is currently in active status within the SPP queue. The utility associated with the project is Springfield, Missouri City Utilities (SPRM).
Generated from interconnection queue and public data sources
State
MO
County
Greene
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPRM
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Summit 161 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- PSLO_MISO_WAUE_OTPW
- POI Substation
- Summit Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-175