SPP-GEN-2024-176
250 MW storage in Reno, KS · In queue since March 2025
250 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-176 is a proposed 250 MW battery storage project located in Reno County, Kansas. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the Reno County 115 kV Substation. The project's service type is listed as ER/NR.
The project is currently listed as active in the SPP queue. The utility is listed as Western Electric Cooperative (WERE). No information is available regarding the developer, proposed commercial operation date, or interconnection agreement (IA) status. The project has not appeared in recent news coverage, nor is it linked to an existing operating plant in EIA data.
Generated from interconnection queue and public data sources
State
KS
County
Reno
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Reno County 115 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- Reno County Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-176