SPP-GEN-2024-177
199 MW storage in Bossier Parish, LA · In queue since March 2025
199 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-177 is a proposed 199 MW battery storage project located in Bossier Parish, Louisiana. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The proposed point of interconnection is the Red Point 138 kV Substation. The project's service type is listed as ER/NR.
The development project is listed as active in the SPP queue. The interconnecting utility is AEP.
Generated from interconnection queue and public data sources
State
LA
County
Bossier Parish
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Red Point 138 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- POI Substation
- Red Point Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-177