SPP-GEN-2024-181
199 MW storage in Greene, MO · In queue since March 2025
199 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-181 is a proposed 199 MW battery storage project located in Greene County, Missouri. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the Brookline 161 kV Substation. The project's service type is Energy Resource/Network Resource (ER/NR).
The project is currently listed as active in the SPP queue. The utility associated with the project is Springfield, Missouri City Utilities (SPRM). The developer is not specified in the queue data.
Generated from interconnection queue and public data sources
State
MO
County
Greene
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPRM
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Brookline 161 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- SPRM_SWCT1
- POI Substation
- Brookline substation