SPP-GEN-2024-189
199 MW storage in Ford, KS · In queue since March 2025
199 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-189 is a proposed 199 MW battery storage project located in Ford County, Kansas. The project, which is interconnected to the ITC Great Plains Saddle 345 kV Substation, entered the Southwest Power Pool (SPP) interconnection queue on March 1, 2025. The designated utility is ITCGP, and the project's service type is Energy Resource/Network Resource (ER/NR).
The project is currently listed as active within the SPP queue. No proposed commercial operation date or interconnection agreement (IA) status is available. Recent news coverage of the project is not available in the provided data.
Generated from interconnection queue and public data sources
State
KS
County
Ford
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
ITCGP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
ITC Great Plains Saddle 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.