SPP-GEN-2024-193
249.6 MW generation in Ford, KS · In queue since March 2025
249.6 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-193 is a proposed wind generation project with a total capacity of 249.6 MW. The project is located in Ford County, Kansas, and is interconnected within the Southwest Power Pool (SPP) region. The project's queue entry date is March 1, 2025. The designated point of interconnection (POI) is the Spearville - Buckner 345 kV Line.
The project, which is listed as active in the interconnection queue, is seeking both Energy Resource (ER) and Network Resource (NR) service types. The utility associated with the project is Sunflower Electric Power Corporation (SUNC).
Generated from interconnection queue and public data sources
State
KS
County
Ford
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Spearville - Buckner 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.