SPP-GEN-2024-205
155 MW generation in Stafford, KS · In queue since March 2025
155 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-205 is a proposed 155 MW solar and battery hybrid project located in Stafford County, Kansas. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The proposed point of interconnection is the St. John 115 kV Substation.
The project, which is listed as active in the queue, is seeking ER/NR service type. The utility is Sunflower Electric Power Corporation (SUNC). There is no information available regarding a developer, proposed commercial operation date, interconnection agreement status, or links to existing operating plants or news coverage.
Generated from interconnection queue and public data sources
State
KS
County
Stafford
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SUNC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
St. John 115 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- POI Substation
- St John
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.