Project SPP-GEN-2024-216 — Project Summary

Queue ID
SPP-GEN-2024-216
Capacity
225 MW
Technology
Wind
Status
active
Location
Custer, MT
Region
SPP
Developer
IA Status

SPP-GEN-2024-216

SPP-GEN-2024-216BetaActiveWind / WindSPPLive · SPP

225 MW generation in Custer, MT · In queue since March 2025

225 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-216 is a proposed wind generation project with a total capacity of 225 MW. The project is located in Custer County, Montana, and is interconnected within the Southwest Power Pool (SPP) region. The Point of Interconnection (POI) is the Miles City 230 kV Substation.

The project entered the SPP interconnection queue on March 1, 2025. The designated utility is WAPA, and the service type is ER/NR. The project's status is currently listed as active within the SPP queue.

Generated from interconnection queue and public data sources

Project Details

State

MT

County

Custer

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

WAPA

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Miles City 230 kV Substation

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
HIGH
Nearest Node (Estimated)
MCWEST
POI Substation
Miles City Substation

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2024-216