SPP-GEN-2024-219
160 MW generation in Murray, OK · In queue since March 2025
160 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-219 is a proposed 160 MW solar and battery hybrid project located in Murray County, Oklahoma. The project consists of both solar photovoltaic generation and battery energy storage, though the individual capacities of each component are not specified. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025.
The proposed project's interconnection point of interconnection (POI) is the Chigley - Oaklawn 138 kV Line, and it is seeking Energy Resource/Network Resource (ER/NR) service. The interconnecting utility is Oklahoma Gas & Electric (OGE). As of the latest data, the project's interconnection status is listed as active.
Generated from interconnection queue and public data sources
State
OK
County
Murray
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Chigley - Oaklawn 138 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-219