SPP-GEN-2024-220
55 MW generation in Caddo Parish, LA · In queue since March 2025
55 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-220 is a proposed 55 MW solar and battery hybrid project located in Caddo Parish, Louisiana. The project is in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on March 1, 2025. The proposed point of interconnection is the Rodessa - Bloomberg 69 kV Line.
The project, categorized as a generation project, is listed as active in the SPP queue. American Electric Power (AEP) is the utility associated with the project. The project is seeking both Energy Resource (ER) and Network Resource (NR) service types.
Generated from interconnection queue and public data sources
State
LA
County
Caddo Parish
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Rodessa - Bloomberg 69 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.