SPP-GEN-2024-221
400 MW generation in Roosevelt, NM · In queue since March 2025
400 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-221 is a proposed 400 MW wind generation project located in Roosevelt County, New Mexico. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the 345 kV Crossroads - Eddy County 345 kV Line, and the utility is SPS. The project's service type is Energy Resource/Network Resource (ER/NR).
The project is currently listed as active in the SPP queue. No proposed commercial operation date or interconnection agreement (IA) status is available. There is no indication of an EIA match to an existing operating plant, nor is there any record of recent news coverage.
Generated from interconnection queue and public data sources
State
NM
County
Roosevelt
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ER/NR
Point of Interconnection
345 kV Crossroads - Eddy County 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- EDDY
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.