Project SPP-GEN-2024-221 — Project Summary

Queue ID
SPP-GEN-2024-221
Capacity
400 MW
Technology
Wind
Status
active
Location
Roosevelt, NM
Region
SPP
Developer
IA Status

SPP-GEN-2024-221

SPP-GEN-2024-221BetaActiveWind / WindSPPLive · SPP

400 MW generation in Roosevelt, NM · In queue since March 2025

400 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-221 is a proposed 400 MW wind generation project located in Roosevelt County, New Mexico. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the 345 kV Crossroads - Eddy County 345 kV Line, and the utility is SPS. The project's service type is Energy Resource/Network Resource (ER/NR).

The project is currently listed as active in the SPP queue. No proposed commercial operation date or interconnection agreement (IA) status is available. There is no indication of an EIA match to an existing operating plant, nor is there any record of recent news coverage.

Generated from interconnection queue and public data sources

Project Details

State

NM

County

Roosevelt

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

SPS

Entity

SPP

Service Type

ER/NR

Point of Interconnection

345 kV Crossroads - Eddy County 345 kV Line

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP South Hub
Hub Confidence
HIGH
Nearest Node (Estimated)
EDDY

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2024-221