SPP-GEN-2024-228
200 MW generation in Rice, KS · In queue since March 2025
200 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-228 is a proposed 200 MW solar generation project located in Rice County, Kansas. The project is in the Southwest Power Pool (SPP) interconnection queue, with an entry date of March 1, 2025. The designated utility is MIDW, and the point of interconnection (POI) is the Rice to Circle 230 kV Line. The project is currently listed as active in the queue and is seeking ER/NR service type.
The proposed project is being tracked within the SPP queue under queue ID SPP-GEN-2024-228.
Generated from interconnection queue and public data sources
State
KS
County
Rice
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
MIDW
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Rice to Circle 230 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.