SPP-GEN-2024-249
721.2 MW generation in Pottawatomie, KS · In queue since March 2025
721.2 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-249 is a proposed 721.2 MW gas-fired generation project located in Pottawatomie County, Kansas. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The designated point of interconnection (POI) is the Jeffrey EC 345 kV Substation. The project's requested service type is ER/NR.
The project is currently listed as active in the SPP queue. The interconnecting utility is Western Resources, Inc. (WERE).
Generated from interconnection queue and public data sources
State
KS
County
Pottawatomie
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Jeffrey EC 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- HIGH
- Nearest Node (Estimated)
- WR.JEC.1
- POI Substation
- Jeffrey Substation
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-249