SPP-GEN-2024-250
199 MW storage in Pittsburgh, OK · In queue since March 2025
199 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-250 is a proposed 199 MW battery storage project located in Pittsburgh County, Oklahoma. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The proposed point of interconnection (POI) is the Pittsburgh 345 kV Substation. The project's service type is listed as ER/NR.
The development project is currently listed as active in the SPP queue. American Electric Power (AEP) is listed as the utility.
Generated from interconnection queue and public data sources
State
OK
County
Pittsburgh
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
AEP
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Pittsburgh 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-250