SPP-GEN-2024-254
300 MW storage in Canadian, OK · In queue since March 2025
300 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-254 is a proposed 300 MW battery storage project located in Canadian County, Oklahoma. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The proposed point of interconnection is the Mathewson 345 kV Substation, and the project is seeking Energy Resource/Network Resource (ER/NR) service.
The project is designated as a hybrid thermal/storage facility in the interconnection queue. Oklahoma Gas & Electric (OGE) is listed as the utility. The project's status is currently "active" in the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Canadian
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Mathewson 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-254