SPP-GEN-2024-258
300 MW generation in Allen, KS · In queue since March 2025
300 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-258 is a proposed 300 MW wind generation project located in Allen County, Kansas. The project is listed in the Southwest Power Pool (SPP) interconnection queue, having entered the queue on March 1, 2025. The designated point of interconnection (POI) is the Wolf Creek - Blackberry 345 kV Line. The project's service type is Energy Resource/Network Resource (ER/NR).
The project developer is unknown, but the interconnecting utility is Northeast Energy & Technology Supply West (NEETSW). The proposed project is currently listed as active in the SPP queue.
Generated from interconnection queue and public data sources
State
KS
County
Allen
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
NEETSW
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Wolf Creek - Blackberry 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.