Project SPP-GEN-2024-260 — Project Summary

Queue ID
SPP-GEN-2024-260
Capacity
199.8 MW
Technology
Battery
Status
active
Location
Buchan, MO
Region
SPP
Developer
IA Status

SPP-GEN-2024-260

SPP-GEN-2024-260BetaActiveBattery/Storage / BatterySPPLive · SPP

199.8 MW storage in Buchan, MO · In queue since March 2025

199.8 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-260 is a proposed 199.8 MW battery storage project located in Buchanan County, Missouri. The project is listed in the Southwest Power Pool (SPP) interconnection queue with a queue entry date of March 1, 2025. The interconnecting utility is Western Energy Resources, Inc. (WERE).

The project's point of interconnection (POI) is the East Town 161 kV Substation. The designated service type is Energy Resource/Network Resource (ER/NR). As of the latest data, the project's interconnection status is listed as active.

Generated from interconnection queue and public data sources

Project Details

State

MO

County

Buchan

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

WERE

Entity

SPP

Service Type

ER/NR

Point of Interconnection

East Town 161 kV Substation

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP North Hub
Hub Confidence
MEDIUM

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.

No ask pi reports yet for this entity.

ask pi about Project SPP-GEN-2024-260