SPP-GEN-2024-261
150 MW generation in Lea, NM · In queue since March 2025
150 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-261 is a proposed 150 MW solar and battery hybrid project located in Lea County, New Mexico. The project, which consists of both solar and battery storage components, is in the Southwest Power Pool (SPP) interconnection queue as of March 1, 2025. The designated point of interconnection (POI) is the Hobbs - LCEC West 115 kV Line.
The project's interconnection service type is Energy Resource/Network Resource (ER/NR). The queue status is currently listed as active. The developer is not specified in the available data. The proposed project is within the service territory of utility LCEC.
Generated from interconnection queue and public data sources
State
NM
County
Lea
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
LCEC
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Hobbs - LCEC West 115 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
No ask pi reports yet for this entity.
ask pi about Project SPP-GEN-2024-261