SPP-GEN-2024-266
500 MW generation in Potter, TX · In queue since March 2025
500 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-266 is a proposed 500 MW solar and battery hybrid project located in Potter County, Texas. The project, which is listed as active in the Southwest Power Pool (SPP) interconnection queue, entered the queue on March 1, 2025. The proposed point of interconnection is the Potter Co - Hitchland 345 kV Line, and the requested service type is ER/NR.
The project consists of both solar and battery storage components, though their individual capacities are not specified. The utility is listed as SPS, and the entity is SPP. The project has appeared in recent news coverage regarding renewable energy development in Texas.
Generated from interconnection queue and public data sources
State
TX
County
Potter
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
SPS
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Potter Co - Hitchland 345 kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.
Top solar plant owners in the US
Data tables and metrics from the powerplantsinfo.org database.
Compare Texas vs California solar
Summary analysis with parallel narrative sections and visualizations.
Top 10 solar states
Data tables and metrics from the powerplantsinfo.org database.