SPP-GEN-2024-268
390 MW generation in Muskogee, OK · In queue since March 2025
390 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-268 is a proposed 390 MW solar photovoltaic generation project located in Muskogee County, Oklahoma. The project is in the Southwest Power Pool (SPP) interconnection queue, with a queue entry date of March 1, 2025. The point of interconnection is the Keefton 345 kV Substation, and Oklahoma Gas & Electric (OGE) is the utility.
The project's service type is Energy Resource/Network Resource (ER/NR), and its interconnection status is listed as active within the SPP queue.
Generated from interconnection queue and public data sources
State
OK
County
Muskogee
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
OGE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Keefton 345 kV Substation
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP South Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.