SPP-GEN-2024-277
150 MW storage in Shawnee, KS · In queue since March 2025
150 MW
Capacity
0
Components
1y 2m
In Queue
—
IA Status
Total Duration
1y 2m
Interconnection request submitted to ISO/RTO
SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.
Typical: 36–48 months (improving)
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial operation date not yet determined
SPP-GEN-2024-277 is a proposed 150 MW battery storage project located in Shawnee County, Kansas. The project, which is in the Southwest Power Pool (SPP) interconnection queue, entered the queue on March 1, 2025. The proposed point of interconnection is the Tecumseh Hill - Swissvale 230kV Line.
The project's service type is listed as ER/NR. The queue status is active. The project is within the service territory of Western Resources (WERE).
Generated from interconnection queue and public data sources
State
KS
County
Shawnee
Grid Region
SPP (Southwest Power Pool)
Market
ISO/RTO Member
Developer
—
Utility
WERE
Entity
SPP
Service Type
ER/NR
Point of Interconnection
Tecumseh Hill - Swissvale 230kV Line
Data Source
Live · SPP
- ISO / RTO
- SPP
- Trading Hub
- SPP North Hub
- Hub Confidence
- MEDIUM
This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.