Project SPP-GEN-2024-278 — Project Summary

Queue ID
SPP-GEN-2024-278
Capacity
264.3 MW
Technology
Wind+Battery
Status
active
Location
Lea, NM
Region
SPP
Developer
IA Status

SPP-GEN-2024-278

SPP-GEN-2024-278BetaActiveHybrid / Wind/StorageSPPLive · SPP

264.3 MW generation in Lea, NM · In queue since March 2025

264.3 MW

Capacity

0

Components

1y 2m

In Queue

IA Status

Interconnection

Total Duration

1y 2m

Pre-Study0%
Queue EntryMar 1, 2025

Interconnection request submitted to ISO/RTO

DISIS Study

SPP uses the Definitive Interconnection System Impact Study (DISIS) cluster process.

Typical: 36–48 months (improving)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

About

SPP-GEN-2024-278 is a proposed wind and battery hybrid project with a total capacity of 264.3 MW. The development is located in Lea County, New Mexico, and is interconnected within the Southwest Power Pool (SPP) queue. The project entered the queue on March 1, 2025, under service type ER/NR, and is currently listed as active.

The project consists of both wind and battery storage components, though their individual capacities are not specified. The point of interconnection (POI) is the Eddy County - Crossroads 345 kV Line, and the interconnecting utility is SPS. There is no information available regarding the developer, proposed commercial operation date, interconnection agreement (IA) status, or any matching operating plant in the EIA database. There is no indication of recent news coverage for this project.

Generated from interconnection queue and public data sources

Project Details

State

NM

County

Lea

Grid Region

SPP (Southwest Power Pool)

Market

ISO/RTO Member

Developer

Utility

SPS

Entity

SPP

Service Type

ER/NR

Point of Interconnection

Eddy County - Crossroads 345 kV Line

Data Source

Live · SPP

Market Context
Approximate
ISO / RTO
SPP
Trading Hub
SPP South Hub
Hub Confidence
HIGH
Nearest Node (Estimated)
EDDY

This project's market context is estimated from its Point of Interconnection. Hub and node assignments are approximate and based on geographic inference from the POI substation name.

No news available for this project.